Short answer
The site coverage of a plot may not exceed 60% of its area, under Article 207 par. 1 case α΄ of the Spatial and Urban Planning Code (Law 5306/2026), ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026, unless a special provision sets another figure. Coverage counts the projection of the outlines of all buildings on a horizontal plane (par. 3) and leaves out the areas listed in par. 4.
What applies today
- Provision
- Article 207 of the Spatial and Urban Planning Code (Law 5306/2026)
- Last amended by
- Not amended
- Last checked
The site coverage (ποσοστό κάλυψης) of a plot may not exceed 60% of its area, under Article 207 par. 1 case α΄ of the Spatial and Urban Planning Code (Law 5306/2026, ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026), unless a special provision sets another figure. This page sets out the general rule, the cases where another percentage applies, and what counts towards coverage. It is a translation of the Greek guide; the Greek text of the ΦΕΚ is the one that applies.
Which provision applies on 11.11.2026
Article 207 of the Code applies, no longer Article 12 of Law 4067/2012. Annex Β΄ of the Code maps Article 12 of Law 4067/2012 to Article 207, and the codified provisions were repealed by Article 477 of the Code.
We found no amendment of Article 207 in any ΦΕΚ Α΄ issue from 89/2026 to 185/09.11.2026, the latest series Α΄ issue we found published on 11.11.2026.
The general rule: up to 60%
The general rule of Article 207 is a maximum site coverage of 60% of the plot’s area (par. 1 case α΄). The same case has two more rules:
- Small plots: where 60% does not give 120 m² of coverage, the maximum rises up to 120 m², provided coverage does not exceed 70% of the plot.
- Areas with the detached building system: where the detached system (πανταχόθεν ελεύθερο) applied on 18.12.1985, and unless special provisions set a lower figure, the maximum coverage is 40% of the plot’s area.
Two definitions of Article 197 of the Code are needed here. Under case 34, the coverage of a plot is the area defined on a horizontal plane by the projections of the outlines of all buildings on the plot, excluding the spaces set out in Article 207. Under case 67, the coverage percentage is the ratio of the maximum area that may be covered to the total area of the plot.
When another percentage applies
60% is a general ceiling, not the figure for every plot. Your plot’s percentage may differ in four cases:
- Special building terms of the area. Under Article 196 par. 5 case α΄ of the Code, special planning provisions prevail over the general provisions of the Section, subject to case β΄.
- Coverage diagrams. Under Article 207 par. 1 case β΄, when town plans are revised, extended or approved, or an area’s building terms are amended, coverage diagrams may be set regardless of percentage.
- A plot with more than one frontage. Under case γ΄, where different coverage percentages apply on the plot’s frontages, the arithmetic mean of the percentages applies to the whole plot.
- Co-owned plots with vertical or horizontal ownership. Par. 2 sets which percentage each co-owner uses when the coverage provisions changed after a permit was issued.
What counts towards coverage: Article 207 par. 3
Coverage counts the projection of the buildings on the ground, together with open semi-outdoor spaces. Under Article 207 par. 3, the calculation counts the area defined by the projections of the outlines of all buildings on a horizontal plane, as those outlines are set by the buildings’ closed and roofed spaces (as in case β΄ of par. 5 of Article 206) and by the open semi-outdoor spaces.
What does not count: Article 207 par. 4
Article 207 par. 4 lists, in cases α΄ to θ΄, the projections that do not count towards coverage:
| What does not count | Condition | Case of par. 4 |
|---|---|---|
| Parts of the open space that recess into the building | Whatever their width and depth | case α΄ |
| Open and closed balconies | No further condition in the case | case β΄ |
| Spaces and structures of Article 206 par. 6 | Cases ι΄, ια΄, ιβ΄, ιγ΄, ιη΄, ιθ΄, κ΄, κα΄, κβ΄, κδ΄, κε΄, κζ΄ and λ΄ | case γ΄ |
| Spaces and structures of Articles 211 and 212 | With the minimum dimensions those Articles set | case δ΄ |
| Atriums, through-openings and vertical shafts | When they start at or below the final ground level, and only for the part not covered by a superstructure | case ε΄ |
| Earth-sheltered buildings or parts of buildings | 50% of the area for residential use, 20% for other uses | case στ΄ |
| Arcade | When built without columns and without a storey above it | case ζ΄ |
| Fire escape stairs | Only in buildings that existed before the fire regulation took effect and have used up their coverage | case η΄ |
| Underground and semi-underground parking beneath open-air sports facilities | Under the conditions of sub-cases θα΄ to θγ΄ | case θ΄ |
For earth-sheltered buildings, case στ΄ adds that coverage may rise, without exceeding 70%.
The mandatory open space
The mandatory open space left in contact with a plot boundary has minimum dimensions. Under Article 207 par. 1 case δ΄, it measures at least δ or Δ. Under Article 198 of the Code, Δ is 3 m + 0.10Η and δ is 2.50 m + 0.05Η, where Η is the building height as that Article defines it.
Outside the plan and in settlements without a plan
Outside an approved town plan, only the rules of Article 207 on what counts towards coverage apply, not the percentage. Under Article 196 par. 2 case ζ΄ and par. 3 case ζ΄ of the Code, outside the plan and in lawfully existing settlements without an approved town plan, pars. 3 and 4 of Article 207 apply. The coverage percentage there is set by the provisions in force for the area.
Worked example
Both examples apply only the general rule of par. 1 case α΄, with no special building terms:
- A 400 m² plot: 400 × 60% = 240 m² maximum coverage.
- A 180 m² plot: 180 × 60% = 108 m², less than 120 m². Coverage rises up to 120 m², which is 66.7% of the plot, below the 70% limit.
Under Article 196 par. 4, every numerical value set in the Section is the maximum permitted. Confirm the percentage that applies to your own plot against the area’s building terms.