Short answer
Until 31.03.2028, only unauthorised structures and changes of use in categories 1 to 4 that were carried out by 28.07.2011 can be declared, under Article 389 par. 1 of the Spatial and Urban Planning Code (Law 5306/2026), ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026. The categories are set in Article 383. Category 5 is not covered by the general rule. The fine is paid with a surcharge, and the text sets no surcharge rate for declarations after 31.03.2026.
What applies today
- Provision
- Articles 383 and 389 of the Spatial and Urban Planning Code (Law 5306/2026)
- Last amended by
- Not amended
- Last checked
Until 31.03.2028, only unauthorised structures and changes of use (αυθαίρετα) in categories 1 to 4 that were carried out by 28.07.2011 can be declared, under Article 389 par. 1 of the Spatial and Urban Planning Code (Law 5306/2026, ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026). This page shows the five categories of Article 383, what stays open until 2028, how the fine is increased, and one point where the text gives no rate. It is a translation of the Greek guide; the Greek text of the ΦΕΚ is the one that applies.
Which provision applies on 11.11.2026
Articles 383 and 389 of the Code apply, no longer Articles 96 and 102 of Law 4495/2017. Annex Β΄ of the Code maps Article 96 of Law 4495/2017 to Article 383 and Article 102 to Article 389, and Article 477 of the Code repealed the codified provisions.
We found no amendment of Articles 383 and 389 in any ΦΕΚ Α΄ issue from 89/2026 to 185/09.11.2026, the latest series Α΄ issue we found published on 11.11.2026.
The first condition: built by 28.07.2011
Only what had been carried out by 28.07.2011 can be declared. Article 383 opens with this cut-off and adds a second condition: the case must not fall under Article 374.
Two checks therefore come before any declaration: the time of construction, and Article 374 of the Code, which sets out when a declaration is prohibited.
The five categories: Article 383
Article 383 sorts unauthorised structures and uses into five categories. The first four lead to permanent exemption from demolition, the fifth to a suspension of penalties.
| Category | What it covers | What is paid | Result |
|---|---|---|---|
| 1 (case α΄) | Structures or changes of use in buildings used mainly as housing, completed before 09.06.1975 | A fee of EUR 250, no single special fine | Permanent exemption from demolition |
| 2 (case β΄) | Structures completed before 01.01.1983 | The fee and the single special fine | Permanent exemption from demolition |
| 3 (case γ΄) | The minor infringements listed in case γ΄, provided they are not covered by Article 316 | A fee of EUR 250, no special fine | Permanent exemption from demolition |
| 4 (case δ΄) | Excesses up to the limits of case δ΄, and changes of use inside town plans that match the permitted uses | The fee and the single special fine | Permanent exemption from demolition |
| 5 (case ε΄) | Whatever is not covered by categories 1 to 4 | The fee and the single special fine | Penalties suspended for 30 years |
Category 3 includes, among others, balconies exceeding their area by up to 20%, openings resized or moved, a pergola of up to 50 m², a storeroom of up to 15 m² with an average height of up to 2.50 m, and changes of up to 5% in the outer dimensions of the outline, provided the area does not change by more than 5%.
Category 4 has five sub-cases:
- an excess of up to 20% in coverage, floor area and height (δα΄),
- an excess of up to 40% in coverage and floor area and up to 20% in height, provided the unauthorised structures do not exceed 250 m² for housing per property and 1,000 m² for the building in total, nor 1,000 m² for other uses (δβ΄),
- structures on properties that hold a building permit, whatever the percentage of excess in coverage or floor area, when they do not exceed 50 m² of total floor area (δγ΄),
- changes of use inside town plans, provided the use matches the permitted uses of the area (δδ΄),
- semi-outdoor spaces in buildings outside town plans, with an excess of up to 60% in coverage and floor area (δε΄).
For the percentages of sub-case δβ΄, the text counts together all unauthorised structures on the property, including those declared under Laws 3775/2009, 3843/2010, 4014/2011 and 4178/2013. The last sentence of case δ΄ leaves out structures that stand more than 20 cm inside the front setback: they are not exempted from demolition.
What can be declared until 31.03.2028: Article 389 par. 1
Only categories 1 to 4 stay open until 2028. Under par. 1 of Article 389, after the general deadline and until 31.03.2028, a declaration is allowed only for unauthorised structures and changes of use in categories 1 to 4 of Article 9 of Law 4178/2013 and categories 1 to 4 of Article 383 of the Code that were carried out by 28.07.2011. The general deadline it refers to is 30.09.2020.
A declaration in this period carries one more condition: the effects of the declaration arise only once the identity of the building, or of the separate property, has been entered in the electronic register.
Category 5: closed, with special cases
Category 5 has not been covered by the general rule since 30.09.2020. Case ε΄ of Article 383 lists special cases with their own deadlines: properties acquired at a forced auction (εγ΄), by inheritance (εδ΄), properties returning after a leasing contract (εε΄), properties transferred to the Public Properties Company (εστ΄), and properties in areas declared in a state of emergency in 2020 (εζ΄).
Those deadlines are tied to 31.12.2025 or to two years from 09.12.2020. In sub-cases εδ΄, εε΄ and εστ΄ the text sets 31.12.2025 as the outer limit. In sub-case εγ΄ the wording is an alternative: the application is filed within one year of the auction award report or by 31.12.2025. Whether a property bought at auction with an award report after 2025 can still be declared is a question of interpretation, and you confirm it before the declaration.
The fine and the surcharges: Article 389 par. 2 to 4
For declarations after 01.10.2020 the single special fine is paid with a surcharge. The fine is calculated under the Annex of Article 399, and par. 3 sets the surcharges by period of declaration:
| Declaration | Surcharge | Case of par. 3 |
|---|---|---|
| 01.10.2020 to 30.09.2021 | 20% | case β΄ |
| 01.10.2021 to 30.09.2022 | 25% | case γ΄ |
| 01.10.2022 to 30.09.2023 | 30% | case δ΄ |
| 01.10.2023 to 30.09.2024 | 35% | case ε΄ |
| 01.10.2024 to 31.03.2026 | 40% | case στ΄ |
Here the text has a gap. Par. 1 says that for declarations from 01.10.2020 to 31.03.2028 the fine is increased under cases β΄ to στ΄ of par. 3, but the last case runs only to 31.03.2026. For declarations from 01.04.2026 Article 389 sets no rate. Confirm in the information system which rate is applied in practice before you calculate the fine for the owner.
Three more rules change the amount:
- A 10% surcharge when the structure or use is in a protection area for which a presidential decree setting building terms is in force (par. 3 case α΄).
- A 10% reduction when a structural adequacy study is filed, and 20% for declarations under Articles 405 and 406 (par. 2 cases γ΄ and δ΄).
- If the competent observatory detects the unauthorised structure or change of use before the date of the declaration, the reductions of par. 2 do not apply and the fine is increased by 20% (par. 4).
Par. 5 to 7 reduce the fine by the cost of works that are completed: adaptation works up to 50%, structural strengthening up to 60%, 50% or 30% depending on the seismic hazard zone, and energy upgrading up to 50% or 30% depending on the size of the excess.
What to check before the declaration
- Document that the structure or change of use had been carried out by 28.07.2011.
- Check that it does not fall under the prohibitions of Article 374.
- Assign a category only after counting together all unauthorised structures on the property. If the total exceeds the limits of category 4, the case falls into category 5 and is not covered by the general rule.
- Confirm the surcharge rate applied on the day of the declaration.
- Plan the entry of the identity of the building or of the separate property. Without it the effects of the declaration do not arise.