Preliminary approval and building permit: when each is needed

Updated

Short answer

A building permit is required for any building work that is not small-scale work, under Article 315 par. 1 of the Spatial and Urban Planning Code (Law 5306/2026), ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026. The preliminary approval (προέγκριση) is optional (Article 321 par. 1) and becomes mandatory in the cases of par. 2, chiefly buildings above 3,000 m² of counted floor area. Without it, a written certificate from the building service comes first (Article 324 par. 2 case β΄).

What applies today

Provision
Articles 315 and 321 of the Spatial and Urban Planning Code (Law 5306/2026)
Last amended by
Not amended
Last checked

A building permit (οικοδομική άδεια) is required for any building work that is not small-scale work, under Article 315 par. 1 of the Spatial and Urban Planning Code (Law 5306/2026, ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026). The preliminary approval (προέγκριση) is optional and becomes mandatory in the cases of Article 321 par. 2. This page shows when each is needed, what the preliminary approval secures, what you submit, and what applies when you go ahead without it. It is a translation of the Greek guide; the Greek text of the ΦΕΚ is the one that applies.

Which provision applies on 11.11.2026

Articles 314, 315, 321, 322, 324 and 329 of the Code apply, no longer Articles 28, 29, 35, 36, 38 and 42 of Law 4495/2017. Annex Β΄ of the Code maps the articles of Law 4495/2017 to the articles of the Code in that order, and Article 477 of the Code repealed the codified provisions.

We found no amendment of these Articles in any ΦΕΚ Α΄ issue from 89/2026 to 185/09.11.2026, the latest series Α΄ issue we found published on 11.11.2026.

When a building permit is required: Article 315 par. 1

A building permit is required for any building work that is not small-scale. Par. 1 of Article 315 says so in general terms and then gives an indicative list, which includes:

  • erecting, extending and repairing buildings (case α΄),
  • demolishing structures, except in the cases of par. 4 (case β΄),
  • excavations or fills deeper than 80 cm, and paving or shaping plots with a view to building (case γ΄),
  • building a swimming pool (case δ΄),
  • a change of use, when it worsens the data of the coverage diagram or the design loads of the structural study, or changes how mechanical installations pass through other floors or shared spaces (case ε΄),
  • works of par. 2 with a budget above EUR 25,000 per horizontal or vertical property (case θ΄),
  • legalising any work already carried out for which a building permit is required (case ι΄).

Under Article 314 case α΄, the term building permit also covers permits that create no floor area, such as the demolition permit and the change-of-use permit, and the earlier term “άδεια δόμησης” means the same thing.

What is covered without a building permit

The Code provides three lighter routes, depending on the work:

  • Approval of small-scale building works (Article 315 par. 2). It covers the works listed in par. 2, cases α΄ to μβ΄. For cases α΄ to η΄, ιθ΄, λ΄, λδ΄ and λε΄ the approval is enough whatever the budget. For the rest, when the total budget exceeds EUR 25,000 per horizontal or vertical property, calculated under the Annex of Article 400, a building permit is required.
  • Approval to carry out works (Article 315 par. 4). It is issued automatically for demolishing dangerously unsound structures, for safety measures on dangerous buildings, and for demolishing or restoring structures finally judged unauthorised.
  • No act at all (Article 316 par. 2). Works such as interior painting and minor repairs to doors and windows need neither a permit nor an approval, subject to special provisions for the area or the building.

What the preliminary approval is and what it secures: Article 314 case γ΄

The preliminary approval certifies the right to obtain the permit and holds the planning figures steady while it is valid. Under Article 314 case γ΄, it is the administrative act that certifies the right to a building permit or a revision permit and the application of the planning provisions and figures (floor area, coverage, height) in force when it is issued. Two conditions apply: the permit is issued while the preliminary approval is valid, and the approvals of Article 326 par. 1 case β΄ are obtained and submitted when the permit is issued.

There is an exception. If street and building lines are amended, if buildable areas are turned into shared public spaces, or if the area is later placed under cultural-heritage or nature protection, the preliminary approval certifies the right to build only as at the time it was issued.

Under Article 329 par. 1, the preliminary approval is valid for two years, whatever the size of the building. The building permit is valid for four years from the day it is granted, and for six years for buildings with a total area above 5,000 m² (par. 2).

When the preliminary approval is mandatory: Article 321 par. 2

The preliminary approval is optional, with three exceptions. Par. 1 of Article 321 makes the procedure optional for every category of permit under Article 322. Under par. 2 it is mandatory:

  • for new buildings with a counted floor area above 3,000 m², and for extensions to existing buildings when the resulting total counted floor area exceeds 3,000 m² (case α΄),
  • where the building permit is issued by a service other than the building service; the local building service then grants the preliminary approval (case β΄),
  • for permanent building installations, works of particular environmental and residential importance or works subject to special control of their building terms, and for buildings above 3,000 m² (case γ΄).

Under par. 3, for permits that fall to the Directorate of Architecture, Building Regulations and Licensing of the Ministry of Environment and Energy, the preliminary approval is mandatory and granted by that Directorate. Under par. 4, no preliminary approval is required for investments that have come or come under Law 3986/2011.

For a revision permit the preliminary approval is optional, where the revision changes the coverage, height and volume figures (par. 1).

What you submit and how long it takes: Article 321 par. 5 to 7

The application is filed electronically through gov.gr with six documents and studies (par. 5):

  1. the application of the owner of the project or the person legally entitled, with the declarations assigning and accepting the studies and their supervision,
  2. a topographic diagram tied to the national coordinate system,
  3. a coverage diagram,
  4. the title deed and a recent ownership certificate, or a cadastral sheet or cadastral diagram extract, for each property,
  5. evidence that the existing structures are lawful,
  6. a technical report describing the project, its sizes and its uses precisely.

The check runs in four steps, each with its own deadline (par. 6):

Step of the check Deadline Case of par. 6
Completeness of documents, studies and data 1 working day from filing case α΄
Title deed and topographic diagram 2 working days from approval of completeness case β΄
Coverage diagram and evidence of lawfulness of existing structures 6 working days from approval of the topographic diagram case γ΄
Issue of the act and the list of what must be filed for the permit 1 working day case δ΄

Under par. 7, the preliminary approval is issued within a strict deadline of 10 days from the electronic filing, when no deficiencies are found. The time between the notice of remarks and the filing of your corrections does not count. You have two months to correct the diagrams, otherwise the application is archived (par. 6 cases β΄ and γ΄). Applications not issued within six months of electronic filing are rejected and archived.

With or without a preliminary approval: Article 324 par. 2

In both cases the permit is issued automatically once the file of Article 326 has been filed electronically. What differs is what comes first:

With preliminary approval (case α΄) Without preliminary approval (case β΄)
What comes first The preliminary approval of Article 321 A written certificate from the building service stating the building terms of the location and the approvals needed. In categories 1 and 2 the topographic diagram is also checked
Deadline Checks within 3 working days of filing the file The certificate is issued within 10 days of the request
What you add Nothing more A solemn declaration by the designing engineer that the building terms and conditions have not changed

For permits issued without a preliminary approval, the building service carries out a sample check of lawfulness on at least 30% of permits, every six months (case β΄). Under par. 3, a check is mandatory on every complaint about the lawfulness of a permit, whatever its category.

Categories 1, 2 and 3 are set in Article 322 par. 1. Category 3 includes, for example, a new building inside an approved town plan of up to 1,000 m² of floor area for special buildings and up to 2,000 m² for buildings used mainly as housing (case γα΄). Category 1 includes every case that does not belong to categories 2 and 3 (case αιγ΄).

What to check before you apply

  • Is the work on the list of Article 315 par. 2 and under EUR 25,000? An approval of small-scale building works is enough.
  • Does the building exceed 3,000 m² of counted floor area, or does another service issue the permit? The preliminary approval is mandatory.
  • Do you expect the building terms of the area to change? The preliminary approval holds the floor area, coverage and height figures for two years, with the exceptions of Article 314 case γ΄.
  • Going ahead without a preliminary approval? Request the certificate of Article 324 par. 2 case β΄ first and allow for its 10 days.
  • For the documents of the file, see the guide to the building permit file.

Sources

  1. Law 5306/2026 ratifying the Spatial and Urban Planning Code (ΦΕΚ Α΄ 88/08.06.2026) (PDF, in Greek)
Written by
Dimosthenis Kanelakis, Co-Founder & COO

An information tool, not legal advice. Professional responsibility remains with the engineer.