Short answer
The Spatial and Urban Planning Code (Law 5306/2026), ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026, has applied since 08.06.2026 and contains no general transitional rule for permits that were pending on that day. Three of its provisions tie a permit to an earlier regime: Article 322 par. 3 for applications in the course of being issued, Article 329 par. 5 for revision after expiry, and Article 273 for building outside town plans, where the deadline is now 30.06.2027.
What applies today
- Provision
- Articles 273, 322 and 329 of the Spatial and Urban Planning Code (Law 5306/2026)
- Last amended by
- Article 273 par. 1: Article 133 of Law 5317/2026 (ΦΕΚ Α΄ 108/10.07.2026)
- Last checked
The Spatial and Urban Planning Code (Law 5306/2026, ΦΕΚ (Government Gazette) Α΄ 88/08.06.2026) has applied since 08.06.2026 and contains no general transitional rule for permits that were pending on that day. This page shows what changed for a file that was already open and which three provisions of the Code tie a preliminary approval or a permit to the provisions of an earlier time. It is a translation of the Greek guide; the Greek text of the ΦΕΚ is the one that applies.
Which provision applies on 11.11.2026
The Code applies, from its publication on 08.06.2026. Article second of Law 5306/2026 puts the law in force from its publication, and Article 477 of the Code repeals, from the day the Code takes effect, the codified provisions listed in its Annex Α΄.
One of the three articles in this guide has been amended. Par. 1 of Article 273 was amended by Article 133 par. 1 of Law 5317/2026 (ΦΕΚ Α΄ 108/10.07.2026), with effect from 01.07.2026 (Article 143 par. 4 of the same law). We found no amendment of Articles 322 and 329, and no later amendment of Article 273, in any ΦΕΚ Α΄ issue from 89/2026 to 185/09.11.2026, the latest series Α΄ issue we found published on 11.11.2026.
What changed on 08.06.2026 for an open file
The provision you cite changed. The Code codifies the provisions that were in force and renumbers them. For permits, Annex Β΄ of the Code gives these correspondences:
| Before 08.06.2026 | In the Code | Subject |
|---|---|---|
| Law 4495/2017, Article 28 | Article 314 | Definitions |
| Law 4495/2017, Article 29 | Article 315 | When a permit or approval is required |
| Law 4495/2017, Article 35 | Article 321 | Preliminary approval |
| Law 4495/2017, Article 36 | Article 322 par. 1 | Categories of permit procedure |
| Law 4495/2017, Article 38 | Article 324 | Checking procedure |
| Law 4495/2017, Article 42 | Article 329 par. 1 to 13 | Validity and revision |
| Law 4759/2020, Article 40 par. 1 | Article 273 par. 1 | Outside town plans, transitional provisions |
We found no general transitional rule that starts from 08.06.2026. The Code’s transitional provisions are the ones carried over from the codified laws, and they keep their own reference dates. So in every pending file you check the three provisions below, not the date of the Code.
Applications in the course of being issued: Article 322 par. 3
An application in the course of being issued is completed under the provisions in force when it was filed. Under par. 3 of Article 322, preliminary approvals and building permits that are in the course of being issued on the date the e-Άδειες information system is modified are completed under the provisions that applied when they were filed.
The same paragraph leaves a choice: a building permit that follows a preliminary approval issued under the earlier provisions may be issued under the provisions of the Code, once the preliminary approval has been revised.
Two points need care:
- The reference date is not a calendar date. It is the date the e-Άδειες system is modified, and under par. 2 the system is adapted by declaratory acts of the President of the Technical Chamber of Greece.
- In Annex Β΄, Article 322 also corresponds to Article 55 of Law 4759/2020. Par. 3 is therefore a rule that existed before the Code. How it applies to an application that was pending on 08.06.2026 is not stated expressly in the text, and you confirm it with the building service.
The preliminary approval you already hold: Articles 314 and 329
A preliminary approval holds the figures of the time it was issued for two years. Under Article 314 case γ΄, it certifies the right to obtain the permit and the application of the planning provisions and figures (floor area, coverage, height) in force when it was issued, provided the permit is issued while it is valid. Under Article 329 par. 1, a preliminary approval is valid for two years, whatever the size of the building.
The protection does not cover three changes: an amendment of street and building lines, the conversion of buildable areas into shared public spaces, and the later placing of the area under cultural-heritage or nature protection. In those cases the preliminary approval certifies the right to build only as at the time it was issued (Article 314 case γ΄).
A permit that has expired: Article 329 par. 5
Which provisions apply to a revision after expiry depends on the stage of construction. A building permit is valid for four years from the day it is granted (par. 2) and is revised after it expires, to extend its validity, on application and after an inspection by a building inspector:
| Stage at expiry | Extension | Provisions that apply | Case |
|---|---|---|---|
| The load-bearing structure is not complete | 4 years from expiry | Those in force when the revision act is issued | case α΄ |
| The load-bearing structure is complete | 4 years from expiry | Those in force when the permit was issued | case β΄ |
| The load-bearing structure, the façades and the roof, where mandatory, are complete and a progress schedule is filed | Indefinite | Those in force when the permit was issued | case γ΄ |
The first row is the one that changes the design: if the load-bearing structure is not complete, the revision follows the provisions of the time of the revision.
Under par. 7, the permits and approvals issued under Law 4030/2011 are revised, as to their period of validity, under what applied when they were issued. When additional building works are carried out, they are revised under the provisions of the Code.
Outside town plans: Article 273 and the 30.06.2027 deadline
For building outside town plans, a permit is issued under the building terms that applied before 09.12.2020 only in the cases Article 273 lists. 09.12.2020 is the date Law 4759/2020 took effect.
Under par. 4, permits are issued under those terms, among other cases:
- if a preliminary approval has been granted or the request for one has been filed (case α΄),
- if the competent planning council (ΣΥ.ΠΟ.Θ.Α.) has approved a derogation (case γ΄),
- if an application with a full architectural study has been filed with the competent service or body, such as the Architecture Council (case δ΄),
- if an application for an excavation permit has been filed with the competent Ephorate of Antiquities (case ε΄),
- if an Environmental Impact Study has been filed or a Decision Approving Environmental Terms has been granted (case ζ΄).
Under par. 5, revisions of permits and preliminary approvals issued under par. 4 continue to be issued under the same terms.
Par. 1 concerns the plots it lists that are buildable by derogation. They may be built on if, until a Local or Special Urban Plan is approved and in any case within two years of 09.12.2020, a request for a preliminary approval or a request for the written certificate of the building service under Article 324 par. 2 case β΄ has been filed. In the second case, the application for a building permit or preliminary approval must be filed by a final date. Article 133 par. 1 of Law 5317/2026 moved that date from 30 June 2026 to 30 June 2027. Under par. 2 of the same Article, the validity of preliminary approvals issued under Article 273 par. 1 is extended to 30.06.2027 where they expire earlier.
What to check in every pending file
- Cite the articles of the Code, using Annex Β΄, in every new document of the file.
- Note the date the application was filed. Which provisions apply under Article 322 par. 3 depends on it.
- Check when the preliminary approval expires. It is valid for two years, and the permit must be issued within them.
- For a permit about to expire, record the stage of the load-bearing structure before expiry. It decides the provisions of the revision.
- For a property outside a town plan, check which case of Article 273 the file relies on and whether 30.06.2027 applies to it.