An act that, for certain categories of project, precedes the building permit and checks the design against the building terms. It is often confused with the building permit, which is the act that allows the project to be carried out.
What it means in practice
Building approval is an intermediate stage in the permit procedure, only for certain categories of project. At this stage it is checked that the project’s design respects the building terms of the location, such as the building coefficient, site coverage, height and the building placement system, before the permit file is complete.
Once the approval is issued, the file is completed with the remaining studies and supporting documents, and the permit is then issued. In this way a problem with the building terms can be found before all the studies are prepared.
Which categories of project require it, what the file includes and how long it is valid are set by the provisions in force.
Common mistakes
- Assuming that building approval allows works to begin.
- Changing the design after approval without checking whether the changes affect what was approved.
- Assuming that every project needs building approval, or that none does, without checking its category.
Difference from the building permit
Building approval checks the design against the building terms and precedes the permit, only in the categories of project where it is required. The building permit is the act that allows the project to be carried out. With building approval alone, works may not begin; the permit must always be issued as well.
Questions
Which projects need building approval?
The categories of project set by the provisions in force. For other projects the permit is issued without a building approval first.
Can works begin with a building approval?
No. Building approval checks the design against the building terms; works begin only once the permit has been issued.
Ask about your own property
Ask using the address or the ΚΑΕΚ (Cadastre property code) and get the article with its ΦΕΚ (Government Gazette issue).
An information tool, not legal advice. Professional responsibility remains with the engineer.